Investments for the 2014 World Cup Foreseen Actions: - Rehabilitation and Expansion of Passengers Terminal and Airplanes Ground Area (1st Phase) Completion: December 2013 Status: Basic Project under execution
- Runway expansion Completion: January 2014 Status: Executive Project under execution
- Implementation of Operational Module Completion: January 2012 Status: CompletedTotal investment: R$ 579.21 million
Operacional Data
|
2011 |
2014 |
| Passengers terminal (m2) |
37.600 |
104.350 |
| Capacity of terminal (year) |
12.0 million |
17.2 million |
| Demand Passengers/year |
7.8 million |
8.8 million |
| Airplanes Ground Area (m2) |
157.930 |
197.130 |
| Veja mais |