Guarulhos - SP

alt

 

Investment Infraero for World Cup 2014: R $ 665.51 million

Actions planned:

- Projects and Work of Expansion and Revitalization System tracks
Completion: December 2011
Status: Work Completed

 

- Implementation of the Passenger Terminal 4 (Phase 1)
End: January 2012
Status: Completed

 

- Work of excavation of the Passenger Terminal 3
Completion: September 2012
Status: Work in implementation

 

- Basic design of the Passenger Terminal 3
End: April 2012
Status: Project in progress

 

Investments of the Concessionaire for the 2014 World Cup: U.S. $ 1.38 billion

 

Concessionaire:'s planned actions:

- Expansion and Revitalization System Track and Patio

- Construction of Ski Taxi and Quick Exit

- Implementation of the Passenger Terminal 4 (Phase 2)

- Construction of Passenger Terminal 3


 

Dados Operacionais 2011 2014
Passengers terminal (m2) 175.700 288.866
Capacity of terminal (year) 25.9 milion 52.7 milion
Demand Passengers/year 29.9 milion 38.9 milion
Airplanes Ground Area (m2)  491.500 801.005

 




 


Veja mais